Public Information Presentation - Carnegie Ave Rehabilitation Phase 3 - East 9th Street to East 55th Street
The purpose of this meeting is to provide important information about the upcoming construction project on Carnegie Avenue
When: July 15, 2026, 5:30 pm
Where: The City Mission 5310 Carnegie Ave., Bldg A Cleveland, OH 44103
TIMELINE:
- Design completed: Fall 2025
- Construction begins: August 2026
- Construction complete: Summer 2027
PROJECT NEED:
We're making changes to Carnegie Avenue to address traffic safety concerns and improve the condition of the roadway.
PROPOSED CHANGES:
- Complete asphalt resurfacing
- Upgrade non-compliant curb ramps to meet accessibility standards
- Replace curbs, sidewalks, and driveway aprons as needed
- Replace existing water main from East 9th Street to East 14th Street
- Realign Prospect Avenue intersection to improve pedestrian safety
- Upgrade signals, new traffic control signs and pavement markings
CONSTRUCTION COST: $8.2 Million Awarded to Terrace Construction
Estimated Cost: $12 million
Funding Sources: Ohio Public Works Commission-Issue 1, City Road & Bridge Bonds and Public Utility Funds