The purpose of this meeting is to provide important information about the upcoming construction project on Carnegie Avenue

When:  July 15, 2026, 5:30 pm    
Where: The City Mission 5310 Carnegie Ave., Bldg A Cleveland, OH 44103

TIMELINE:

  • Design completed: Fall 2025
  • Construction begins: August 2026
  • Construction complete: Summer 2027

PROJECT NEED:
We're making changes to Carnegie Avenue to address traffic safety concerns and improve the condition of the roadway.

PROPOSED CHANGES:

  • Complete asphalt resurfacing
  • Upgrade non-compliant curb ramps to meet accessibility standards
  • Replace curbs, sidewalks, and driveway aprons as needed
  • Replace existing water main from East 9th Street to East 14th Street
  • Realign Prospect Avenue intersection to improve pedestrian safety
  • Upgrade signals, new traffic control signs and pavement markings

CONSTRUCTION COST: $8.2 Million Awarded to Terrace Construction

Estimated Cost: $12 million 
Funding Sources: Ohio Public Works Commission-Issue 1, City Road & Bridge Bonds and Public Utility Funds