Lee Road Corridor Revitalization - Miles Avenue to Invermere Avenue - Business Focus Group Meeting
The purpose of this meeting is to provide important information about the upcoming project on Lee Road.
When: September 3, 2026, 9:30 am - 11:00 am
Where: Harvard Community Center 18240 Harvard Avenue
TIMELINE:
- Design completed: December 2027
- Construction begins: June 2028
- Construction complete: May 2031
PROJECT NEED:
We're making changes to Lee Road to address traffic safety concerns and improve the condition of the roadway.
PROPOSED CHANGES:
- Reconstruct 1.22 miles of Lee Road from Miles Avenue to Invermere Avenue
- Add a multiuse path along the west side of the road
- Replace curbs, sidewalks, and driveway aprons as needed
- Streetscaping and drainage upgrades
- ADA - compliant facilities throughout the project limits
- Upgrade signals, new traffic control signs and pavement markings