Fulton Road Phase II Rehabilitation Project

Tuesday, October 1, 2019

CLEVELAND – On Monday October 7, 2019, the City will begin construction of the Fulton Road Phase II Rehabilitation Project from Lorain Avenue to Detroit Avenue (0.8 miles). This phase will include a new water main and connections repair and resurfacing of existing roadway pavement, replacement of damaged curbs, drive aprons, and sidewalks where needed, ADA-compliant curb ramps, upgrades to traffic signals, new pavement markings and bicycle facilities. The intersection at Franklin Boulevard will be reconstructed as a roundabout.

Maintenance of traffic will be as follows:

  • One-way southbound traffic will be maintained.
  • Northbound traffic will travel west on Lorain Avenue, then north on west 45th Street and then east on Detroit Avenue.

The work will take place Monday through Friday, 7 a.m. to 5 p.m. The project is scheduled for completion in October 2020.

Questions? Contact the City of Cleveland’s Construction Inspector, Cecil Benson at 216-857-7648

Editor’s Note: Road construction invariably presents hazards to the public. All travelers are urged to use caution in construction zones. Public safety and the safety of workers is a top priority.

About the City of Cleveland

The City of Cleveland is committed to improving the quality of life of its residents by strengthening neighborhoods, delivering superior services, embracing diversity and making Cleveland a desirable, safe city in which to live, work, play, and do business. For more information on the City of Cleveland, visit online at www.city.cleveland.oh.us, Twitter at @cityofcleveland or Facebook at www.facebook.com/cityofcleveland.